Carmarthenshire Council Forecasts £68 Million Underspend on Capital Projects, Cabinet Reveals

news.wales / newyddion.cymru
This article is old - Published: Tuesday, Mar 19th, 2024

CARMARTHENSHIRE Council is forecasting a £68 million underspend on projects like new schools and regeneration schemes, cabinet was told.
Councillors had agreed to spend £139 million on a range of capital projects in 2023-24 when they set the budget last March. This sum factors in income like grants and revenue from new buildings, as well as design and construction costs. Delayed projects will be included in the capital budget for coming financial years.
The latest forecast presented to cabinet is that the council will  spend just under £71 million rather than £139 million. This figure is a snapshot from the end of December so it could change by the end of this month when the financial year ends.
Cabinet members expressed satisfaction with what was being achieved, such as the recent completion of a new Pembrey primary school.
“We are working and developing in so many areas,” said cabinet member for education and Welsh language, Cllr Glynog Davies. “New schools are needed in this county, and we want to continue to do that.”
The biggest chunk of this year’s capital budget was a planned £63 million expenditure on regeneration projects, but the latest forecast is much lower – £21 million. The report said this decrease was due to delays to Swansea Bay City Region projects and the revamp of the former Debenhams store in Carmarthen into a new community hub, among other things.
The housing department is expecting to spend £6 million less than the £34 million it planned, partly due to delays in a new homes project in Tyisha, Llanelli.
Meanwhile, £5 million less is being allocated to the long-awaited Towy Valley cycle path than planned in 2023-24 due to delays, and a £3 million underspend is forecast on new fleet vehicles because of long lead-in times to acquire them.
The education and children’s department expects to spend £4 million less on new projects than anticipated for reasons including that Welsh Government approval for them is still pending.
Cllr Alun Lenny, cabinet member for resources, said the housing department was still due to spend a notable sum of more than £28 million in 2023-24, including £8 million bringing empty properties back into use and over £4 million on new council homes. A total of 20 new flats have recently been created at former council offices on Spilman Street, Carmarthen, and the old YMCA building on Stepney Street, Carmarthen.
Cllr Linda Evans, cabinet member for homes, welcomed these new flats while acknowledging that demand for affordable and social housing was “extremely high”. She said: “It’s very hard for people out there at the moment.”
The council’s largest capital project – the £200 million Pentre Awel health and well-being complex in Llanelli – is making progress, and the first of four phases is due to open this autumn. The first phase will include a new Llanelli leisure centre.
Councils everywhere experience delays in their capital programme, and Carmarthenshire underspent the previous year – 2022-23 – by £46 million, according to that year’s statement of accounts.
One side effect of a slippage in capital expenditure is that councils can earn interest on the money it’s borrowed for the projects but not actually spent. It can also hold off borrowing, therefore incurring fewer repayment costs. In Carmarthenshire’s case this has resulted in a £3 million boost to the council’s revenue, or day-to-day, budget for 2023-24.
The £3 million is badly needed for revenue budget reasons because council departments are forecast to overspend by more than £10 million, driven largely by high demand for specialist children’s services and agency staff costs, and increased adult social care expenditure. In addition to this, schools are expected to spend £8.6 million more than planned, partly due to wage rises, which would take schools’ overall level of reserves down to just £2.5 million.
Finance chiefs are using the £3 million sum, plus £1.5 million from the council’s contigency fund, to reduce revenue overspending.
Cllr Lenny said he believed that the financial outlook would worsen for all councils next year. He added: “I can assure all members of the continued prudent financial management of the authority.” ‌​‌​‌​​​‍‌​‌​​‌‌‌‍‌​‌‌​​‌​‍‌​‌‌‌​‌‌‍‌​‌‌‌‌​​



Spotted something? Got a story? Email News@News.Wales



More from Carmarthenshire Council

Sewer Burst in Carmarthenshire Village Raises Concerns Over Housing Development

Carmarthenshire Council

Group Continues Fight to Save Village Pub Despite Planning Permission for Conversion

Carmarthenshire Council

Residents of Salem, Carmarthenshire, Rally to Save The Angel Inn

Carmarthenshire Council

Plans Paused to Amalgamate Schools’ Governing Bodies in Carmarthenshire

Carmarthenshire Council

New Drive-Through McDonald’s Nears Approval in Carmarthenshire

Carmarthenshire Council

Owner of Loss-Making Village Pub Criticises Local Group’s Takeover Bid

Carmarthenshire Council

Latest from News.Wales

Further £1.2m Council Funding for Redevelopment of The British at Talywain

Torfaen Council

Patients in Powys hospitals to be grouped by specific need from this autumn

Powys Council

Protests Outside Council Offices in Pontypridd Over Controversial Quarry Extension

Rhondda Council

Councillors to Approve Transfer of Trusteeship for Presteigne Memorial Hall

Powys Council

Former Council Staff Removed from Local Government Pension Scheme

Torfaen Council

Search for Gypsy and Traveller Sites in Wales to Start Over, Councillors Say

Monmouthshire Council