Work to lay new electrical cables in a Newport industrial estate could cause up to four months of disruption.
The city council’s planning committee has unanimously approved the laying of 1.5 kilometres of underground cables at the Celtic Technology Centre, near Duffryn.
At a meeting on Wednesday (December 6), planning officer Grant Hawkins told the committee the cables would serve a data centre following an “increase in demand for power”.
A nearby substation will soon “reach capacity”, he added.
The applicant, Vantage Data Centres, will carry out the works along the carriageway of Dyffryn Lane and Celtic Way in 30-metre sections, laying the cable in a trench, which will then be backfilled before workers move onto the next section.
The planning committee was reminded the site was close to reens belonging to the protected Gwent Levels area, but council documents show planning officers were “generally satisfied” with the applicant’s details of pollution prevention. ‌​‌​‌​​​‍‌​‌​​‌‌‌‍‌​‌‌​​‌​‍‌​‌‌‌​‌‌‍‌​‌‌‌‌​​



Spotted something? Got a story? Email News@News.Wales



More from Newport Council

Plans to Toughen Antisocial Behaviour Rules in Newport Win Council Support

Newport Council

Newport Waste Bosses Implement “Carrot and Stick” Approach to Boost Recycling

Newport Council

Plans to modernise an old farm building in Penhow spark controversy with Newport City Council

Newport Council

Dominant 5G Mobile Phone Mast Rejected in Newport Neighbourhood

Newport Council

Major Changes to Newport Schools in New Academic Year

Newport Council

Question raised over closure of Pill Library in Newport, Wales

Newport Council

Latest from News.Wales

Swansea Council Staff Exit Packages Total £1.62 Million in 2023-24

Swansea Council

Trial Scheme for Overnight Motorhome Parking in Pembrokeshire Expected to be Dropped, New Facility at Fishguard Ferry Considered

Pembrokeshire Council

Plans Submitted for New Natural Memorial Garden at Pembrokeshire Crematorium

Pembrokeshire Council

National Trust’s Plans for Tilting Weir and Walkway Approved Despite Concerns

Pembrokeshire Council

New Group Takes Over Swansea Airport Operation

Swansea Council

Pembroke Dock’s Anchorage Day Centre Faces Closure Amid Council Changes

Pembrokeshire Council