Posted: Mon 29th Jul 2024

Building Firm Appointed for £3.7m Redevelopment of Council Farm

news.wales / newyddion.cymru
This article is old - Published: Monday, Jul 29th, 2024

A BUILDING firm has been appointed to carry out the £3.7 million redevelopment of a council run farm attraction. 
Construction at Greenmeadow Community Farm, in Cwmbran, could take nine months, or 36 weeks, which is six weeks longer than anticipated by Torfaen council but its cabinet was told any impact on its expected April 2025 opening date will be reported to it. 
The Labour run council’s cabinet approved the contract in a special meeting this week which it was also agreed cannot be called in for review, by back bench councillors, as it was an urgent decision due to the timescales involved. 
G Oakley and Sons was awarded the contract to revamp existing buildings as well as build a new play barn and animal barn and improve the entrance. 
The small working farm has been closed to the public since autumn 2022 when Torfaen County Borough Council agreed to revamp its attractions to make it commercially viable. 
However spiraling cost meant the original plans were shelved and the council, in September last year, agreed to provide a further £1.6m for the overhaul of the site. 
Cwmbran Coed Eva councillor Fiona Cross, who is responsible for communities, said: “This is a huge step in the journey we’ve been on with the farm. Once we get spades in the ground I’m sure officers, and myself, will be relived.” 
Pontnewydd member Sue Morgan said it is still anticipated the farm will be open before the school holidays in 2025 and said it was important it didn’t miss out the holiday period. 
At the full council meeting, which followed the special cabinet session, Cllr Cross told Llantarnam independent member David Thomas, who had asked for an update, a general manager had been appointed in February. 
The council had received four tenders for the work with the contract awarded on the basis of 60 per cent quality consideration and price 40 per cent. The contractor has suggested some cost-saving ideas while time saving ideas will also be discussed. All contracts came in over the 30 week construction period ‌​‌​‌​​​‍‌​‌​​‌‌‌‍‌​‌‌​​‌​‍‌​‌‌‌​‌‌‍‌​‌‌‌‌​​

By BBC LDRS ‌​‌​‌​​​‍‌​‌​​‌‌‌‍‌​‌‌​​‌​‍‌​‌‌‌​‌‌‍‌​‌‌‌‌​​



Spotted something? Got a story? Email News@News.Wales



More from Torfaen Council

Gwent Council Plans to Partner with German Energy Giant for Wind Turbine Project

Torfaen Council

Gwent’s Newest Welsh Medium School Sees Enrollment Grow From 3 to 20

Torfaen Council

Householder Told “Six Foot” Fence in Garden Must Go

Torfaen Council

Welsh Councils Express Concerns Over Elimination of For-Profit Care Homes

Torfaen Council

Concern Raised Over Disabled Child Unable to Access Science Block Without Lift

Torfaen Council

Reducing number of children in residential care to address Gwent council’s projected overspend

Torfaen Council

Latest from News.Wales

Tories Oppose Pay Rises for Council Chiefs, Decline Committee Involvement

Monmouthshire Council

School Redundancies Looming as Monmouthshire Schools Face £6 Million Overspend

Monmouthshire Council

Gwent Council Plans to Partner with German Energy Giant for Wind Turbine Project

Torfaen Council

Swansea Council staff took 12.6 sick days on average, meeting told

Swansea Council

Gin Distillery and B&B Scheme Turned Down by Pembrokeshire Planners

Pembrokeshire Council

River Pollution Poses Major Threat to Housing Developments and Economic Prosperity in Powys, Warns Councilors

Powys Council